APPENDIX B-08
****DRAFT****

RCIP Comparison of Year 2000 Lanes Miles to General Plan Buildout Lane Miles
LANE-MILES
  FREEWAYS
RAMPS
HOV/
RAMPS
MAJOR
ARTERIAL
PRIMARY
ARTERIAL
SECONDARY
ARTERIAL
TOTAL
2000 1072.40 27.37 138.46 1388.58 2020.32 4,647
BUILD 2272.45 88.08 1555.06 3243.16 3092.55 10,251
Difference (Build-2000) +1,200 +61 +1,417 +1,855 +1,072 +5,604
Cost/lane mile* $10,250,000 $4,134,675 $2,900,000 $2,900,000 $2,900,000  
Estimated Cost $12,300,512,500 $251,016,119 $4,108,140,000 $5,378,282,000 $3,109,467,000 $25,147,417,619
6/26/2002
* Cost Assumptions Per Lane Mile:
Arterials Construction $850,000
  ROW $600,000
  Planning-10% $145,000
  Engineering-35% $507,500
  Contingency-20% $290,000
  Major Structures-35% $507,500
  Total $2,900,000
HOV/Ramps Construction $1,275,000
  ROW $900,000
  Planning-10% $2,175
  Engineering-35% $761,250
  Contingency-20% $435,000
  Major Structures-35% $761,250
  Total $4,134,675
Freeways Construction $4,000,000
  ROW $1,000,000
  Planning-10% $500,000
  Engineering-35% $1,750,000
  Contingency-20% $1,000,000
  Major Structures-40% $2,000,000
  Total $10,250,000

 

 


 

 

ASGNGRP LANE-MILES ASGNGRP LANE-MILES
1 2125.91 1 941.96
2 1555.06 2 138.46
3 3243.16 3 1388.58
4 3092.55 4 2020.32
5 88.08 5 27.37
7 31.32 7 21.86
8 115.22 8 108.58
9 0 9 0
  10,251   4,647