Volume 1 - SECTION 8.0

RCIP Comparison of Year 2000 Lanes Miles to General Plan Buildout Lane Miles
LANE-MILES
 FREEWAYS
RAMPS
HOV/
RAMPS
MAJOR
ARTERIAL
PRIMARY
ARTERIAL
SECONDARY
ARTERIAL
TOTAL
20001072.4027.37138.461388.582020.324,647
BUILD2272.4588.081555.063243.163092.5510,251
Difference (Build-2000)+1,200+61+1,417+1,855+1,072+5,604
Cost/lane mile*$10,250,000$4,134,675$2,900,000$2,900,000$2,900,000 
Estimated Cost$12,300,512,500$251,016,119$4,108,140,000$5,378,282,000$3,109,467,000$25,147,417,619
6/26/2002
* Cost Assumptions Per Lane Mile:
Arterials Construction$850,000
 ROW$600,000
 Planning-10%$145,000
 Engineering-35%$507,500
 Contingency-20%$290,000
 Major Structures-35%$507,500
 Total$2,900,000
HOV/Ramps Construction$1,275,000
 ROW$900,000
 Planning-10%$2,175
 Engineering-35%$761,250
 Contingency-20%$435,000
 Major Structures-35%$761,250
 Total$4,134,675
Freeways Construction$4,000,000
 ROW$1,000,000
 Planning-10%$500,000
 Engineering-35%$1,750,000
 Contingency-20%$1,000,000
 Major Structures-40%$2,000,000
 Total$10,250,000

 

ASGNGRPLANE-MILESASGNGRPLANE-MILES
12125.911941.96
21555.062138.46
33243.1631388.58
43092.5542020.32
588.08527.37
731.32721.86
8115.228108.58
9090
 10,251 4,647