Inspections & Requirements: Roof Mount Solar

1st Inspections:

  • Ground electrode
  • Rough electrical
  • Grounding and bonding
  • Service panel
  • Framing
  • Final

Items to be on site at time of inspection and other items:

  • Job card.
  • Approved plans.
  • All rough electrical is to be exposed.
  • Smoke detector certification form signed by contractor.
  • Solar layout and all other placards.
  • Photo of solar panel identification tag. (photos from phone are not acceptable unless the field inspector verifies, they were taken at the time of inspection)
  • Ladder set up and secured to building with 3 steps above the roof.

Inspections & Requirements: Ground Mount Solar

1st inspection:

  • Set-backs footings and forms
  • Steel and hardware
  • Conduit

2nd inspection:

  • Final (protective barrier required to protect underside, solar Scrim or barrier)
  • Ground electrode
  • Rough electric (all electrical is to be exposed)
  • Grounding and bonding
  • Service panel
  • Framing

Items needed at Final:

  • Job card
  • Smoke detector certification
  • Solar layout placard at main panel and all other placards
  • Approved plans

Inspections & Requirements: Panel Upgrade/ Roof mount Solar/ Combo Inspection

Inspections: Sometimes this gets split up into 2 inspections and 2 releases

If broken up into 2 inspections -

1st inspection will be: Service Panel (You will be required to have your panel 100% complete and all electrical exposed, schedule as follows):

2nd inspection:

  • Ground electrode
  • Rough electrical
  • Grounding and bonding
  • Service panel, (this may be scheduled prior to final of permit to release power, upgrade and/or derate breaker must be ready)
  • Framing Final

Items to be on site at time of inspection and other items:

  • Job card
  • Approved plans
  • All rough electrical is to be exposed
  • Smoke detector certification form signed by contractor Solar layout and all other placards
  • Photo of solar panel identification tag (photos from phone are not acceptable unless the field inspector verifies, they were taken at the time of inspection)
  • Ladder set up and secured to building with 3 steps above the roof