Limonite Ave Interchange at I-15: Hamner Ave to Wineville Ave

Recon and widen overpass and ramps

Details

Project Manager:
John Marcinek

Lead Agency:
Riverside County Transportation Department

Construction Labor Provided By:
Contractor

Hot Project:
Yes

Caltrans Involvement:
Oversight

Community Councils:
 

Municipal Advisory Councils:
 

Road No's:
S2089A

Location

SD: 2

MD: 14

RD BK: 14B

Finance ($ in thousands)
Task Budget
(Total)
Spent
(Total)

(%)
Budget
(FY17)
Spent
(YTD)

(%)
Spent
(Last Month)
Totals $69,505 $8,146 12% $8,604 $216 3% $121
Preliminary Survey $383 $393 103 $
Environmental Docs & Clearance $2,445 $1,784 73 $150 $1 1 $
Design (PS&E) $2,690 $2,405 89 210 $94 45 $53
Right-of-way Aquisition $12,482 $3,552 28 $8,074 $119 1 $67
Utility Relocations $1,380 $150
Construction $42,275 $9 $20 $ 1 $
Construction Engineer & Inspect $6,300 $
Construction Survey $1,550
Source PSV ENV DES RWE UTL CON CEI CSV Total
Totals $383 $2,445 $2,690 $12,482 $1,380 $42,275 $6,300 $1,550 $69,505
Mira Loma R & B Benefit District $383 $2,445 $2,690 $12,482 $1,380 $775 $800 $550 $21,505
SB-132 $41,500 $5,500 $1,000 $48,000
Progress Open 5-Year Lookahead PDF Schedule